Details of Ongoing Schemes as on 01-04-2005 under the Rural Water Supply Programme

Rural Water Supply Programme

As on 1.4.05 there are 1,231 ongoing schemes under the programme: 477 under MNP/PMGY, 407 under ARWSP and 347 under the Prime Minister's Programme. The estimated cost of these schemes varies from a few thousand rupees to several crores.

Of these ongoing schemes, 471 (38.26%) were sanctioned during the last financial year, 2004-05, and 352 (28.59%) are physically completed, with only financial liabilities to be cleared. The zone-wise position of total ongoing schemes, the number sanctioned during 2004-05 and the number physically completed are at Annexure II (PDF) (opens in a new window).

9 schemes have remained incomplete for more than 10 years due to theft of pipes or disputes, 24 for more than 5 but less than 10 years, and 171 have been under implementation for more than 2 but less than 5 years. Division-wise details are at Annexure III (PDF) (opens in a new window).

The amount required to complete these ongoing schemes is Rs. 124.96 crore. Programme-wise requirement:

Programme-wise amount required to complete ongoing rural water supply schemes, as on 01-04-2005
ProgrammeAmount required (Rs. crore)
MNP/PMGY84.79
ARWSP39.09
Prime Minister's Programme1.08
Total124.96

See also Annexure IV (PDF) (opens in a new window) (programme-wise). The zone-wise amount required to complete the ongoing schemes is at Annexure V (PDF) (opens in a new window).

Urban Water Supply Programme

Seven schemes are under implementation under the State sector Urban Water Supply Programme, of which one is physically completed. In addition, the State share for three centrally sponsored schemes has to be provided from the State Plan. The amount required to complete these ongoing schemes is Rs. 22.19 crore.

Under NLCPR, there are two ongoing projects: Tura Phase-III WSS and Jowai WSS. They are funded by DoNER (Department for Development of North Eastern Region, Government of India). The amount required to complete these two schemes as on 1.4.05 is Rs. 25.91 crore, of which Rs. 5.74 crore has already been released by DoNER.

Under the centrally sponsored AUWSP, there are two ongoing schemes: Simsanggiri (Williamnagar) WSS and Baghmara WSS. Simsanggiri WSS was commissioned during 2004-05 and only financial liabilities are to be cleared. Work on Baghmara WSS is in progress.

Under the Central Pool, the scheme for improvement of municipal sources is in good progress and is expected to be completed by March 2006.

Implementing Divisions

17 working divisions are implementing these schemes. The names of the divisions and sub-divisions, and the list of officers, are at Annexure VI (PDF) (opens in a new window).

Division-wise details of ongoing schemes, programme by programme, are in the Division-wise details.

Conclusion

It is the endeavour of the Department to complete all schemes within the scheduled time. However, due to shortage of funds and other reasons such as theft, disputes over land/source, inter-village rivalry and delays in completing work, implementation of schemes is sometimes delayed. The system of reviewing and monitoring the implementation of schemes has been strengthened. PHED will make every effort to provide adequate safe water supply from the schemes to the intended population within the scheduled time of completion.